Create A Layer Of Concrete Front yard

Garage to street driveway


Making a concrete slab driveway is a challenging task. Preparing the job for the concrete pour is less of a challenge and can be accomplished easily by most handy homeowners. The preparation work involves grading, simple form setting, placement of rebar, and setting overheads or screeds. However, the actual pouring, placing and finishing of a large area of concrete is a job that is best accomplished with professional assistance. Since concrete placement and finishing can be contracted separately from form setting and preparation, you may save a good deal of money by doing the preparation yourself.


Instructions


1. Grading for slab


Level the soil. The soil must be solid enough to support the weight of the concrete. Grade the slab area to a level 3 1/2 inches below the level of the garage floor. The soil should be graded to allow about 1/4 inch to the foot (1 percent) fall away from the garage on the final concrete surface for water drainage. If there is no garage involved in your project set your form finish level to 3 1/2 inches above the finish grade level of the pad on which the drive is to be located.


2. Staking forms


Mark out the perimeter of the drive, including the side against the garage, using your twine and chalk. Using the square blade shovel, dig 12-inch by 6-inch footings at all edges of the slab to prevent edge breakage. Typical driveways from garage to street are 16-feet wide, to allow two-car parking.


3. Batter board to line forms


Nail together 2-by-8 boards to run from the sidewalk to the garage slab. Line up the inside face of the form with your layout twine, which should be placed on batter board or offset stakes (see picture below). Drive 1-by-2 stakes vertically behind the form boards every 4 feet using the twine to keep the boards straight.


4. Pouring colored concrete


Set your layout twine with a 1 percent fall-away from the building, then nail your forms to the stakes. This will provide the necessary drainage.


5. Kicker stakes


Drive 1-by-2 stakes at a 45-degree angle behind the form boards every 4 feet using the twine to keep the boards straight. Place temporary kicker stakes inside the forms to keep the forms braced until the concrete is poured.


6. Cutting rebar


Place 1/2-inch rebar, top and bottom, in the perimeter footing hung off the form boards on tie wire. This rebar should be placed at all four sides of the driveway slab.


7. Steel mat in slab


Cut and place 3/8-inch rebar at 24 inches on centers to form a steel mat in the driveway slab area. The mat should run at right angles to the garage door to start. Tie off the mat to the rebar in the footings to provide continuous reinforcement in the driveway slab.


8. Finishing concrete


Place 2-by-4 overheads to form bays which are 10 feet by 16 feet from one end of the drive to the other. Cut 2-by-4 screeds with 1-by-2 ears on each end of the screed to fit in each bay to level concrete as it is poured. The overheads or screeds are nailed to 1-by-2 stakes or set in special metal screed pins so that the bottom of the screeds is the actual finish level of the driveway.


9. Premix truck


Place the concrete from low end to high end. Premix and pumping is generally used by professional finishers. The concrete is pumped in to fill all bays equally and rodded off to achieve a roughly level finish surface. The overheads are pulled out and thrown aside. The concrete is tamped, allowed to cure, if necessary, and hand or machine finished with a steel trowel tor a smooth, slick finish.


10. Broom finish


Apply the final finish after the slab is level and smooth. The most common finish is a non-slip, which is applied with a stiff bristle broom. Expansion joints are scribed into the slab surface with V trowels and the job is completed.








Related posts



    The hardness of concrete is determined basically by two things--the mixture of the ingredients and the time you allow for the concrete to set, or cure. The important elements in the mixing of conc...
    Use concrete slurry to bond new concrete to old concrete.Concrete slurry is used as a glue to bind old concrete to new concrete. It is especially helpful when patching cracks or holes in existing...
    Installing concrete structures in or near saltwater.A marine or saltwater environment is devastating to normal concrete. The salt in the air or water degrades the integrity of normal concrete caus...
    A dress form will help with measuring when sewing clothes.Sewing your own clothes is a satisfying, money saving hobby. You can make the clothes you want to fit your exact shape, which a store boug...
    Baseboard heaters offer a convenient heating alternative to traditional forced-air furnace systems. Whereas forced-air heaters warm air and push it through a duct system to different rooms in the...